The Owner Builder Process: Step by Step Guide

Part of our Complete Guide to Owner Builder Kit Homes

Building your own kit home is a major project. This guide walks you through every phase from initial planning to moving in.


Phase 1: Planning and Research (4-8 weeks)

  • Research owner builder requirements in your state
  • Determine your total budget with 10-15% contingency
  • Browse kit home floor plans and request quotes
  • Commission soil test and site survey
  • Check BAL rating for bushfire zones

Phase 2: Permits and Approvals (6-14 weeks)

  • Complete owner builder course (1-2 days)
  • Apply for owner builder permit
  • Finalise kit home design with supplier
  • Lodge plans with council or private certifier
  • Receive building permit

Phase 3: Pre-Construction (2-4 weeks)

  • Arrange construction and public liability insurance
  • Install temporary fencing, power, and toilet
  • Get quotes and book trades
  • Establish site access for trucks

Phase 4: Foundation (2-4 weeks)

  • Site clearing and levelling
  • Install services rough-in
  • Formwork and reinforcement
  • Pre-pour inspection
  • Concrete pour and cure time

Phase 5: Kit Delivery and Frame (1-3 weeks)

  • Kit home delivered to site
  • Check components against manifest
  • Erect wall frames and roof trusses
  • Frame inspection

Phase 6: Lock-Up (4-8 weeks)

  • Roof sheeting, flashings, gutters
  • External cladding
  • Windows and external doors
  • Lock-up inspection

Phase 7: Internal Fit-Out (8-14 weeks)

  • Plumbing and electrical rough-in
  • Insulation and plasterboard
  • Waterproofing and tiling
  • Kitchen and joinery
  • Painting and flooring

Phase 8: Completion (2-4 weeks)

  • Electrical and plumbing final fix
  • Final inspections
  • Occupancy certificate
  • Move in

Typical Timeline: 7-15 months total